Langston Chapel Rd.-Harville Rd. roundabout opening delayed by Hurricane Helene

The new roundabout at Harville Rd. and Langston Chapel Rd. was expected to open this week, but according to GDOT, that opening has now been delayed until October 22 due to Hurricane Helene.
langstonharville-107
Road work continues on the new roundabout | DeWayne Grice

The opening of the new roundabout at Harville Rd. and Langston Chapel Rd. was originally scheduled for today, Monday, October 7. According to GDOT, though, that opening has now been delayed until October 22 due to Hurricane Helene.

Crews are currently paving the roadway. Please DO NOT drive around the barricades in the work zone. This endangers the workers who are trying to complete this job.

img_7968
Work continued on Monday, October 7, 2024; Please do not drive around barricades | DeWayne Grice

JA Long Inc. closed the intersection in July for a projected 90 days to construct a roundabout at the location for the Georgia Department of Transportation.

The below closure and detour information was provided at the start of the project.

harvillerd-july2024

The work also includes a road closure and detour along Elmer Phillips Road at Harville Road. Elmer Phillips traffic will use Highway 67 as a detour. See a map below.

elmerphillips-july2024

The closures and detours will be in place until the project is complete.

If you have any questions regarding these shutdowns or require any additional information, please contact JA Long Project Manager Brandon Bloomfield at (706) 566-9161 or [email protected].